Update on W Little Creek Rd Sewer Replacement

Update from city’s project manager:

  • Work on Little Creek is scheduled to start early April 2024.
  • Current traffic control to remain in place to avoid the city sewer bypass line.
  • Traffic control will be modified when construction starts, due to obstacles that include existing power lines and depth of the sewer.
  • One lane east and one lane west shall remain open during construction. 
  • Estimated completion ins August 2024 (due to the large roadway restoration in Little Creek Rd involving concrete replacement).
  • A project bulletin will be sent out shortly with corresponding city contact information, schedule, and details as similarly stated above.

Also, an update for Wards Corner PS 150 Phase 7:

  • Work progressing east along Warren Street towards Granby Street.
  • Newport Avenue traffic is open fully, water and sewer complete. Small concrete/pavement restoration will occur for a few days in the near future at intersection of Newport & Warren at a later time/date.     
  • Work remains ahead of schedule and is anticipated to be complete by the end of the year 2024.